- Home
- Your Government
- Departments
- Engineering
- City Improvement Projects
- 2024 PROJECTS
- Barthels Rum River Acres & White Pines Estates Street Reconstruction IP24-01
Barthels Rum River Acres & White Pines Estates Street Reconstruction IP24-01
October 17, 2023
A public open house meeting for Barthels Rum River & White Pines Estates Street Reconstruction will occur from 5:30 – 6:30 PM on Thursday, November 2, 2023, in the Lake Itasca Room at the Ramsey Municipal Center. The purpose of the meeting is to present information on the proposed project to owners of the properties that are directly impacted by this project.
An informal presentation detailing the proposed project, along with funding sources will be shared.
September 1, 2023
City Improvement Project #24-01 proposes to reconstruct the streets within the Barthel’s Rum River Acres and White Pines Estates subdivision, generally located between 164th Lane and 165th Lane, adjacent to the Rum River. This project is included in the 2023 – 2032 Capital Improvement Program (CIP) for reconstruction in 2024. Property Owners will not be assessed for these improvements.
On August 22, 2023, the Ramsey City Council ordered Staff to prepare plans and specifications for this improvement project. Plans will be developed over the next several months, before going back to City Council to approve the final plans and authorize Staff to advertise the project for bids.
Preliminary Project Schedule:
- Aug – Dec 2023 Staff prepares plans and specifications.
- Jan – Feb 2024 City Council approves plans and authorizes bidding. More information will be available once the City Council meeting date for plan approval is set.
- Feb – Mar 2024 Bids are received and publicly opened. City Council awards a construction contract to the lowest responsible bidder.
- May – June 2024 Anticipated start of construction; this will be impacted by the Contractor’s proposed schedule. Construction may not start until the summer months.
- Summer 2024 Project construction
Proposed Improvements:
Subsurface evaluation of the streets found a mix of materials well suited for pavement support, and materials that will require removal and replacement. Staff is proposing to use the current typical City pavement section of 4 to 6-inches aggregate base under 3.5-inches bituminous pavement. The specific parameters of the sub-soil corrections, removal and replacement of material not suited for pavement support, will be determined during project design. For areas not requiring sub-soil corrections, the proposed pavement section is anticipated to be achieved by reclaiming (grinding up) the existing bituminous pavement and aggregate base, hauling and stockpiling this material, re-using the reclaimed material as aggregate base, and placing 3.5-inches of new bituminous pavement.
The existing streets have a mix of rural sections with drainage swales adjacent to the pavement and urban sections with bituminous curbing. The rural section street will continue to have drainage swales, the bituminous curbing will be replaced with concrete curb & gutter, as the concrete curb is superior to bituminous curb.
Municipal sanitary sewer and watermain do not exist in project area and are not proposed to be extended to the project area with this project.
Stormwater runoff from the pavement is directed into drainage ditches along the sides of the roadways. There are no known issues with stormwater management in the project area, and no improvements to the existing drainage ditches are proposed with this project. The areas of the project with bituminous curbing, will be upgraded to concrete curb and gutter with storm sewer inlets placed in the flowline of the gutter. During design, Staff will further evaluate stormwater management to ensure that no additional stormwater improvements are necessary. If you are aware of any stormwater drainage issues in the immediate area, please contact us to let us know about the issue.
Property Impacts:
Access to abutting properties will be maintained throughout construction as best as practical. City Staff will work with all property owners during construction to ensure they are informed in advance of any work that will affect and/or interrupt access to their property for any length of time, particularly due to reconstructing driveway aprons. Access for emergency services will be maintained throughout construction.
Private lawn irrigation systems and underground invisible fences may be impacted by this work. Relocating and/or repairing private irrigation systems within public right of ways as needed to accommodate construction is the responsibility of the property owner. If you have a below-ground irrigation system, you will be asked to mark your sprinkler heads with flags or stakes to assist the Contractor in preventing or minimizing damage to your system during construction. To help ensure that your system will not be damaged during the project, please relocate sprinkler heads and other system components located within the construction limits. City Staff will mark construction limits for you upon request.
November 30, 2023
City Improvement Project #24-01 proposes to reconstruct the streets within the Barthel’s Rum River Acres and White Pines Estates subdivision; generally located between 164th Lane and 165th Lane, adjacent to the Rum River.
On November 28, 2023, the Ramsey City Council approved the plans and specifications and authorized advertisement for bids for this project. Staff is proposing to open bids for the project on February 21, 2024.
Preliminary Project Schedule:
- February 21, 2024; bids will be opened and reviewed to ensure they comply with all bidding requirements.
- February 27, 2024; the lowest responsible bid will be presented to City Council for award of a construction contract.
- Spring 2024; the Contractor may begin construction. Before construction begins, the City and Contractor hold a pre-construction meeting, during which the Contractor provides their proposed construction schedule. Another letter will then be mailed with more specific construction information.
- August 2, 2024; the Contractor substantially completes construction, including finishing all driveway repairs, utility repairs, and having the new bituminous pavement in-place.
- August 31, 2024; the Contractor reaches final completion on the project, including creating a punch list of any minor repairs still required on the job.
Proposed Improvements:
Subsurface evaluation of the streets found a mix of materials well suited for pavement support in the roadway embankment area. Areas of silt and highly plastic clay exist below the roadway embankment zone; however, these will only impact the project if excavation goes deeper than 3 to 4 feet, generally for storm sewer installation. Where these soils are found during pipe installation, the plans call for subsoil corrections for storm sewer pipe bedding and backfill.
In general, the current swales along the streets within Barthel’s Rum River Acres subdivision are not proposed to be re-graded as part of this project. Due to the nature of street reconstructions, the in-slopes will be disturbed approximately 3 to 5 feet off of the edge of pavement. The existing culverts crossing the streets are proposed to be removed and replaced with concrete culverts. This is to ensure the culverts will last at least through the proposed 60-year design life of the street.
The bituminous curbing within the White Pines Estates subdivision is proposed to be replaced with surmountable concrete curb and gutter. At driveways, a curb cut similar will be placed to avoid a high transition from the roadway to driveways. Additionally, concrete storm sewer catch basins and pipe will be added to better drain the urban section streets.
Restoration of the impacted boulevard areas will include a minimum of 4-inches topsoil and hydroseed with a residential turf seed mix. Though the pavement is generally going back to the same location and elevation, driveway aprons will be replaced to match into the new bituminous pavement as minor changes will occur. In general, driveway aprons will be going back 8 feet to tie the driveways into the new pavement. The project does not propose to replace driveway culverts.
Property Impacts:
Access to abutting properties will be maintained throughout construction as best as practical. City Staff will work with all property owners during construction to ensure they are informed in advance of any work that will affect and/or interrupt access to their property for any length of time, particularly due to reconstructing driveway aprons. Access for emergency services will be maintained throughout construction.
Private lawn irrigation systems and underground invisible fences may be impacted by this work. Relocating and/or repairing private irrigation systems within public right of ways as needed to accommodate construction is the responsibility of the property owner. If you have a below ground irrigation system, you will be asked to mark your sprinkler heads with flags or stakes to assist the Contractor in preventing or minimizing damage to your system during construction. To help ensure that your system will not be damaged during the project, please relocate sprinkler heads and other system components located within the construction limits. City Staff will mark construction limits for you upon request.
Project Funding:
The engineer’s opinion of probable costs for the proposed improvements is $1,505,111. Estimated costs include 23-percent indirect costs for administrative, engineering, finance, and legal costs. The improvements are proposed to be funded using a combination of Pavement Management Funds and Stormwater Utility Funds. Again, property owners will not be assessed for these improvements. This is an estimate based on proposed quantities and anticipated 2024 construction costs. The final project costs may vary dependent upon actual bid prices and quantities.
June 27, 2023
The Ramsey City Council awarded a proposal from Independent Testing Technologies, Inc. to complete a geotechnical report for Barthel’s Rum River Acres and White Pines Estates subdivision.
The geotechnical report will require 17 soil borings, all of which will be taken in the streets. You can expect to see a soil boring truck and crew members. The streets will remain open to traffic during the soil borings. A firm schedule of when this work will be performed is not known, but you should expect it to occur within the next several weeks.
Before soil boring can occur, the Contractor will call Gopher One State to locate utilities in the area, so you will likely see paint and flag markings within the project area.
June 13, 2023
The Ramsey City Council awarded a proposal from Bolton & Menk, Inc. to complete a topographic survey for Barthel’s Rum River Acres and White Pines Estates subdivision.
The topographic survey will be taken across the entire City-owned right of way, and will include survey of the street, drainage swales, any light poles, signs, trees, landscaping, and driveways up to the right of way. You can expect to see a crew of 2-3 surveyors, and a pick-up truck. The work is scheduled to begin the week of June 19, and be complete by June 30.
Part of the topographic survey includes surveying existing utilities, both municipal and private, such as cable, gas, and electric lines. Bolton & Menk will call Gopher One State to locate utilities in the area, so you will likely see paint and flag markings within the project area.
This work is being done to assist with design for the future reconstruction of the Barthel’s Rum River Acres and White Pine Estates subdivision. These streets are proposed to be reconstructed in 2024, as identified in the City’s current 10-year Capital Improvement Program. This work is preliminary, City Council has not yet approved plans and specifications for this project.
-
Stacie Damjanovich
Administrative AssistantPhone: 763-433-9895
-
Joe Feriancek
Assistant City EngineerPhone: 763-433-9893