Posted on: July 27, 2020

Construction on Variolite Street

Raod Work


Construction started on August 3rd. For current weekly information check the project web page.

The City will be reconstructing 2.25 miles of Variolite Street between Alpine Drive and 173rd Avenue. The work is estimated to include:

  • 37,705 square yards of stabilized full depth pavement reclamation
  • 19, 543 square yards of stabilized full-depth pavement reclamation (not stabilized)
  • 12,576 tons of bituminous pavement
  • 458 lineal feet of culvert
  • 371 lineal feet of drain tiles and;
  • Miscellaneous other improvements