Woodlands

Developer

Lennar Homes

Summary of Project

  • 7566 159th Avenue Northwest
  • 85 detached single-family lots 
  • Completed in multiple phases

Plans

Construction Status

  • Phase 1 - Public infrastructure is substantially complete for Phase 1 (26 lots). Only final lift of asphalt and final testing of Trunk Sanitary Sewer System remains. Additional phases will be reviewed as submitted by Developer. Lots are available for purchase from Developer. 
  • Phase 2 - The City has approved a second phase consisting of fifteen (15) lots. Construction has commenced.
  • Phase 3 - The City has approved a third phase consisting of thirty (30) lots. Construction will commence upon completion of Phase 2 and will occur in 2016.
  • Phase 4 - This City is currently reviewing the fourth and final phase. 

For more information, email the Community Development Department or call at 763-433-9824, or view the Development Updates page.